Program Overview
MCC’s $238 million Liberia Compact (2016-2021) aimed to encourage economic growth and reduce poverty by providing access to more reliable and affordable electricity. The compact funded the $207 million Energy Sector Project, which included rehabilitating the Mount Coffee Hydropower Plant to generate 75 megawatts of low-cost renewable energy. Activities also included supporting the management services contract to strengthen the Liberia Electricity Corporation’s management and operations capacity, and establishing an independent regulator to accelerate private sector investment in the energy sector.
Evaluator Description
MCC commissioned Mathematica to conduct an independent final performance evaluation of the Liberia Energy Sector Project. Full report results and learning: https://mcc.icpsr.umich.edu/evaluations/index.php/catalog/231.
Key Findings
Power Plant Rehabilitation and Electricity Access
- Customer connections grew quickly as the Mount Coffee Hydropower Plant and donor-funded distribution projects were completed.
- Plant sustainability is jeopardized by inadequate funding for operations and maintenance.
Management Services Contract and Utility Capacity
- Despite challenges, the management services contract, which the firm hired to support the utility, increased connections, reduced outages, and improved management practices.
- Power theft remains high and threatens sustainability. The utility requires investments in meters and the low voltage network to meet customer demand.
Energy Sector Regulation
Evaluation Questions
The final performance evaluation was designed to answer whether the project:
- 1
Was implemented as planned? - 2
Contributed to improvements in electricity regulation, policy formulation, and monitoring? - 3
Affected electricity generation, transmission, distribution, and reliability? - 4
Aided in the sustainability of the Liberia Electricity Corporation as a utility? - 5
Affected the number of users connecting to the grid and the demand for electricity?
Detailed Findings
These findings build upon the interim evaluation report results published in 2020.
Power Plant Rehabilitation and Electricity Access
The Mount Coffee Hydropower Plant was rehabilitated, providing access to low-cost hydropower during the rainy season (from May to October) at a cost of $0.14 per kilowatt hour (kWh) compared to $0.33 per kWh for thermal generation.
In January 2021, one of the units of the power plant failed, and the unit remained offline at the time of data collection. Design and construction choices may have led to the catastrophic failure. Repair costs were estimated at $4-$9 million, and lost revenue may exceed $5 million to date. Additional units may require a similar repair.
The Liberia Electricity Corporation, the power utility, estimated connections grew from 35,000 customers in 2018 to 157,000 by March 2022. While overall demand has increased, average customer consumption has declined over time. Most households report their main use of electricity is for lighting. More than 60 percent of leaders in communities surveyed between late 2020 and late 2021 reported that health facilities, pharmacies, and schools have Liberia Electricity Corporation electricity, compared to 15 percent in 2019. However, end users report that more hours of reliable power are needed to improve business productivity and operations.
Management Services Contract and Utility Capacity
Electricity Supply Board International (ESBI) became the management services contractor in 2018. At the time, the Liberia Electricity Corporation operated at a loss and debt exceeded $21 million. The utility also had lawsuits for unpaid fuel, loans for inoperable equipment, contracts due to cronyism, burnt records, no asset listing, no customer database and a low voltage network requiring extensive repair. With widespread power sector corruption, the utility’s financial crisis, and increasing responsibilities with new donor-funded assets, the contract lacked operating investments, capital investments, and Board of Directors support.
Still, ESBI succeeded in extending the transmission and distribution network. ESBI reduced outages and increased overall demand and the number of actively paying customers. Power theft and political interference remain the utility’s greatest threats to solvency and sustainability. The Liberia Electricity Corporation has lost $271.9 million from 2015 to 2021, including $15.9 million in unpaid bills, $204 million in commercial losses, and $51.9 million in technical losses. More generated power has meant greater losses.