A multifaceted development approach requires proactive and visionary management.

A multifaceted development approach requires proactive and visionary management. The Irrigated Agriculture Project suffered from poor integration of project activities and targeting of beneficiaries. Project activities were broken into several different contracts, which increased the challenge of coordination among contractors’ timelines and activities. Mid-course corrections such as improvements in coordination among contractors, implementation strategy and staffing changes reduced the risks inherent in the piecemeal implementation approach, which improved implementation performance. Nonetheless, sequencing challenges compromised the original program logic.